While the school has been closed for the summer holidays, steady progress has been made on the new site. Foundations are complete and substructure brickwork has commenced on the school building. Drainage is almost complete. Foundations, drainage and substructure brickwork are complete for the residential block. The new access road tarmac base course, drainage and kerbs are complete. The approved Inspector visits the site on a regular basis and is happy with all the works.